Africazine:
The National Water and Electricity Company is nearing completion of a vital water project in The Gambia.
The OIC Water Project, aimed at rehabilitating water and sanitation networks, is currently about 80 percent complete. NAWEC officials anticipate finalizing the project by June, addressing the water supply gap in the Greater Banjul Area.
NAWEC Showcases Progress on OIC Water Project
Today, NAWEC conducted a media tour to highlight key sites involved in the OIC Water Project. The tour included various implementation sites where ongoing works were documented. Senior management provided briefings on the project’s objectives and current status.
The initiative is crucial for improving water supply and sanitation in the Greater Banjul Area. By enhancing infrastructure, the project aims to meet the growing demand for clean water in the region.
The Gambia: Key figures on OIC Water Project
- 80 percent completion
- Expected finalization by June
Future Steps for the OIC Water Project
- Finalization of the project by June
The OIC Water Project is set to significantly improve water access in The Gambia.